Case Study

Addenbrooke’s Hospital – Pathology Laboratories

  Location:  Addenbrooke's Hospital – Fourth & Fifth Floors, Pathology Wing

  Value of Works:  £890,000

  Time on Site:  14 Months - Phased Programme

Purpose of the Project

To refurbish areas across the fourth and fifth floors of the hospital’s Pathology Wing to enable the installation of new pathology equipment while allowing the wider department to remain operational.

Works Undertaken on Site

The project was delivered across six separate phases over a 14-month programme.

Temporary fire-rated partitions were installed to isolate each work area from the live department. ABC then delivered the required mechanical and electrical services and finishes within each phase.

Individual areas were completed and formally handed over before staff occupied them and the programme progressed to the next phase.

Full handover and witnessing of the installed systems was undertaken on completion.

Challenges

Maintaining operational pathology services throughout the programme was the principal challenge.

Careful phasing was essential to ensure construction activities, equipment installation and the continuing use of adjacent areas could operate safely alongside one another.

ABC’s Site Manager and Project Manager worked closely with the hospital estates team, equipment supplier and users to coordinate programme dates for each phase.

The M&E design was similarly developed around the hospital’s existing systems, with user meetings helping to ensure the completed installations met operational requirements.