Addenbrooke's Hospital – Fourth & Fifth Floors, Pathology WingProject Outline:To refurbish areas across the fourth and fifth floors of the hospital's Pathology Wing to enable the installation of new pathology equipment while allowing the wider department to remain operational.
-
Kent and Canterbury HospitalProject Outline:To refurbish an existing CT suite and associated control room within a live hospital imaging department, preparing the area for replacement imaging equipment and associated services.
-
King's College Hospital - First FloorProject Outline:To alter and adapt an existing hospital area to create two new angiography examination rooms together with the associated clinical, patient and technical accommodation. -
Stoke CDCProject Outline:To deliver the specialist environments required for a new multi-modality diagnostic imaging facility, incorporating X-ray, CT and MRI accommodation within a larger construction project. -
Andover War Memorial HospitalProject Outline:To carry out a complete refurbishment of an existing X-ray room within a live department, including changes to improve bed access and accommodate a revised equipment layout.
-
Royal Hampshire County Hospital - Second FloorProject Outline:To replace two existing mammography rooms within the department while minimising the overall period of disruption to the hospital's mammography service.
-
Princess Elizabeth Hospital, GuernseyProject Outline:To replace the existing fluoroscopy system within Fluoroscopy Room 3, while improving the layout of the space and creating a better working and patient environment. The new installation changed the orientation of the equipment and relocated electrical plant outside the main examination room.
-
St Thomas' Hospital - First FloorProject Outline:To replace an existing MRI system that had been out of service for almost 12 months, restoring an important imaging facility for patients and clinical teams as quickly and safely as possible.
-
Andover War Memorial HospitalProject Outline:To deliver a new, single-storey MRI imaging suite at Andover War Memorial Hospital, providing the local community and surrounding areas with improved access to MRI services and reducing the need for patients to travel to alternative facilities. -
Hammersmith HospitalProject Outline:Replacement of existing obsolete PET CT with a pet CT of the latest technology for detailed high level reserch. -
Basildon General HospitalProject Outline:Replacement of 4 existing obsolete Catheter Labs. -
Southampton General HospitalProject Outline:Installation of 2 magnetic resonance imaging (MRI) systems designed by Siemens Healthcare Systems for imaging of Neurological patients. -
LiverpoolProject Outline:A multi-modality equipment project which was originally undertaken by a previous main contractor, and which was then taken over for completion by another contractor. -
BirminghamProject Outline:Upgrade of the existing Siemens MRI scanner to a newer platform. -
HartlepoolProject Outline:Replacement of the current Siemens Healthineers MRI scanner.
Case Study
Royal Victoria Infirmary – Angiography Lab
Location: Royal Victoria Infirmary, Newcastle
Value of Works: £300,000
Tender & Design Period: 40 Weeks - Design and HRB Approval Process
Time on Site: 13 Weeks
Purpose of the Project
To refurbish an existing angiography laboratory and control room, preparing the clinical environment for new specialist imaging equipment while working within the requirements applicable to a Higher-Risk Building.
Works Undertaken on Site
ABC developed a full design package for approval before works commenced and subsequently delivered the mechanical and electrical services and internal finishes required within the refurbished Angio Lab and control room.
To provide a viable construction access route, ABC formed a temporary opening from an adjacent main corridor incorporating a three-hour fire-rated double door set.
Following completion of the works and installation and testing of the imaging equipment, the temporary access was removed and the wall fully reinstated.
Challenges
The project fell within Higher-Risk Building requirements, meaning the complete design package had to pass through the relevant approval process before construction could begin. This process took approximately 40 weeks.
The Angio Lab itself is positioned within the heart of the operating theatre environment. Normal access would have required construction traffic to pass through clean clinical areas, which was not considered acceptable.
The temporary access solution allowed works to be separated from those sensitive areas while regular project reporting and coordination with the hospital estates team ensured ABC continued to work in accordance with the approved designs.
The project was subsequently completed on time and to programme.