Addenbrooke's Hospital – Fourth & Fifth Floors, Pathology WingProject Outline:To refurbish areas across the fourth and fifth floors of the hospital's Pathology Wing to enable the installation of new pathology equipment while allowing the wider department to remain operational.
-
Kent and Canterbury HospitalProject Outline:To refurbish an existing CT suite and associated control room within a live hospital imaging department, preparing the area for replacement imaging equipment and associated services.
-
Royal Victoria Infirmary, NewcastleProject Outline:To refurbish an existing angiography laboratory and control room, preparing the clinical environment for new specialist imaging equipment while working within the requirements applicable to a Higher-Risk Building.
-
King's College Hospital - First FloorProject Outline:To alter and adapt an existing hospital area to create two new angiography examination rooms together with the associated clinical, patient and technical accommodation. -
Stoke CDCProject Outline:To deliver the specialist environments required for a new multi-modality diagnostic imaging facility, incorporating X-ray, CT and MRI accommodation within a larger construction project. -
Andover War Memorial HospitalProject Outline:To carry out a complete refurbishment of an existing X-ray room within a live department, including changes to improve bed access and accommodate a revised equipment layout.
-
Princess Elizabeth Hospital, GuernseyProject Outline:To replace the existing fluoroscopy system within Fluoroscopy Room 3, while improving the layout of the space and creating a better working and patient environment. The new installation changed the orientation of the equipment and relocated electrical plant outside the main examination room.
-
St Thomas' Hospital - First FloorProject Outline:To replace an existing MRI system that had been out of service for almost 12 months, restoring an important imaging facility for patients and clinical teams as quickly and safely as possible.
-
Andover War Memorial HospitalProject Outline:To deliver a new, single-storey MRI imaging suite at Andover War Memorial Hospital, providing the local community and surrounding areas with improved access to MRI services and reducing the need for patients to travel to alternative facilities. -
Hammersmith HospitalProject Outline:Replacement of existing obsolete PET CT with a pet CT of the latest technology for detailed high level reserch. -
Basildon General HospitalProject Outline:Replacement of 4 existing obsolete Catheter Labs. -
Southampton General HospitalProject Outline:Installation of 2 magnetic resonance imaging (MRI) systems designed by Siemens Healthcare Systems for imaging of Neurological patients. -
LiverpoolProject Outline:A multi-modality equipment project which was originally undertaken by a previous main contractor, and which was then taken over for completion by another contractor. -
BirminghamProject Outline:Upgrade of the existing Siemens MRI scanner to a newer platform. -
HartlepoolProject Outline:Replacement of the current Siemens Healthineers MRI scanner.
Case Study
Royal Hampshire County Hospital – Mammography Rooms
Location: Royal Hampshire County Hospital - Second Floor
Value of Works: £122,500
Tender & Design Period: 10 Weeks
Time on Site: 3 Weeks
Purpose of the Project
To replace two existing mammography rooms within the department while minimising the overall period of disruption to the hospital’s mammography service.
The decision was taken to undertake both rooms simultaneously, reducing available capacity during the works but enabling the complete programme to be delivered within just three weeks.
Works Undertaken on Site
ABC coordinated the refurbishment and preparation of both mammography rooms around the requirements of the replacement equipment.
Because of the relatively compact nature of the rooms, the design approach was kept deliberately clean and minimal, developed in collaboration with hospital staff and users to make effective use of the available space.
Challenges
The department is located on the second floor of an extremely busy hospital where external space and parking are at a premium.
It was therefore not possible to establish a conventional site compound or skip area. Waste removal and site logistics had to be carefully planned to avoid interference with patients, staff and normal hospital activities.
Despite the restricted programme and working environment, both rooms were successfully completed on time and within budget.